Warsaw Trams can now fully use the newly built Annopol Depot. The Annopol depot had been planned since the 1960s, and the construction of the depot was in question, because in Warsaw in the 60s and 70s trams were threatened with liquidation. In 2024, the construction of the fifth tram depot in Warsaw, which is the most modern depot in Poland and one of the most modern in Europe, was completed. As part of the project, Railway gft Polska Sp. z o. o. supplied materials, including: 60R2 and 49E1 rails and track accessories for fastening systems.
Investor: The Capital City of Warsaw and Warsaw Trams Ltd.
Contractor: Consortium - ZUE S.A. (Leader)
Implementation period: 08.12.2021 - 17.10.2024
Contract value: PLN 715,794,304.83